Making Products that people use

Hercules technician uses a reactor flask in the laboratory, circa 1960.

Hercules technician uses a reactor flask in the laboratory, circa 1960.

rosin_building_at_np193b18d_0_x346d5217_download_full.jpeg
Hercules Brunswick facility, circa 1960.

Hercules Brunswick facility, circa 1960.

As a major economic force, Hercules grew along with Brunswick. The Brunswick facility, located on Glynn Avenue near the causeway bridge, had a long history of manufacturing operations that spanned more than a century. With the exception of the Great Depression years, it operated since 1911, using pine tree stumps to make rosin and other products.

Since the advent of state and federal environmental regulations, much has been accomplished to address the environmental legacy of these historical operations.

In 2023, a fire caused the permanent shut down of the facility. In 2025, demolition activities on the physical structures of the facility were completed. Remediation at the site did not stop and is still continuing with a focus toward reuse of the property. 

100+ Years of History

Generations of Brunswick people worked at the Brunswick facility when it was operated by Hercules, and then by Pinova from 2010 through 2023. Even after its operations ceased, Hercules has been conducting environmental remediation and restoration at three sites in Brunswick. A timeline summarizing the history of operations and remediation at these three sites is below.

 
  •  Brunswick facility 
  •  009 Landfill 
  •  Terry Creek 
  • Sediment dredged in Terry Creek

    Sediment dredged in Terry Creek


    Sediment removed in Terry Creek

    Sediment removed in Terry Creek


    Lining of the N-Street Ditch

    Lining of the N-Street Ditch


    Sampling sediment from Terry Creek

    Sampling sediment from Terry Creek


    Collecting field samples

    Collecting field samples


    Monitoring fish tissue in Terry Creek

    Monitoring fish tissue in Terry Creek


    Monitoring fish tissue in Back River

    Monitoring fish tissue in Back River


    Collecting soil samples

    Collecting soil samples


    Workers implement “ISS” remedy at the plant


    Soil being loaded for disposal


    Constructing the new channel


    Excavator working on OU1 remedy


    Scrap metal being segregated during plant demolition


    Soil excavation at the plant


    Capping of OU1 with telebelt system to create sand cap


    Lining of outfall ditch before sand and soil placement


    Gate installed to prevent manatees from swimming into culvert


    Rock dam installed along Dupree Creek


    Investigation of marsh areas near the site


    1911 The Brunswick naval stores plant opened, using an innovative new process to extract rosin from pine tree stumps.
    1920 Hercules began operating at the Brunswick facility, producing rosin and turpentine from pine stumps.
    1914 - 1944 Hercules corporation entered the war efforts, producing smokeless powder during World War I and munitions during World War II at some of its other plants. In 1944, the Brunswick facility was awarded the Army-Navy E flag for its contributions to the Allies' victory.
    1946 Hercules began to produce a new insecticide called "toxaphene" to combat boll weevils in the South. Some wastewater from the toxaphene production plant at the facility was conveyed through a ditch to Dupree Creek.
    1949 Hercules' chemists continued to develop and refine new products. The workforce grew to nearly 800 people.
    1950 Railroad capacity at the Brunswick facility expanded. Agricultural demand for toxaphene increased.
    1951 The workforce at the Brunswick facility grew to 900 people.
    1957 A new unit began producing rosin used to make synthetic rubber.
    1960s The plant continues to prosper and adopt new technologies (Labors of a Modern Hercules, D. Dyer, 1990).
    1970s - 1980s The U.S. Army Corps of Engineers dredged Dupree and Terry Creeks, placing the dredged spoils in three areas along the creeks.
    1980 Production of toxaphene ended.
    1980s Hercules began to investigate and remediate the site. Wastewater impoundments located in the northern portion of the facility were closed and the waste was disposed in a secure landfill. A groundwater monitoring well network was installed.
    1984 The **009 Landfill** was placed in the federal Superfund program.
    1990s Hercules continued investigation and remediation at the plant. It removed and remediated an equalization basin and above-ground storage tanks in the northern portion of the facility and conducted biological treatment in the area to prevent contaminants from being carried in groundwater.
    1993 EPA approved Hercules' remediation plan for the 009 Landfill.
    1995 - 2009 Hercules installed and operated a groundwater pump and treat system to extract and treat groundwater from the northern portion of the Brunswick facility.
    Mid-late 1990s Hercules removed and disposed of soils found under the former toxaphene production plant, down to the groundwater table.
    1997 Hercules began extensive sampling of soil and sediment at the Terry Creek site under EPA oversight.
    1999 Hercules completed construction of the 009 Landfill cap and installed a comprehensive monitoring system.
    1999 - 2000 Hercules removed approximately 30,000 tons of contaminated sediments from the outfall ditch and adjacent creeks and entered into an agreement with EPA to evaluate risks and additional remediation.
    2000s Hercules continued its investigation to identify areas to be remediated. Hundreds of acres, above and below ground, were sampled and studied extensively.
    2001 The state conducted fish tissue sampling showing improvement in fish tissue quality after Hercules’ remediation of the outfall ditch and creeks.
    2005 Hercules resumed the state's fish tissue sampling, confirming continued improvements in fish tissue quality.
    2005 Hercules leases a portion of the 009 Landfill cap to be used by the neighboring auto dealer as a part of its car lot. An asphalt cap is built on top of the exisitng landfill cap.
    2007 The state relaxed fish consumption advisories after remediation activities in the outfall ditch and the adjacent creeks resulted in improvements.
    2008 - 2010 Hercules remediated the former toxaphene production plant and the N-Street ditch: demolishing the plant, excavating 47,000 tons of soil from the plant and the ditch, backfilling the plant area, and relining the ditch.
    2010 Pinova purchased the operational portions of the Brunswick facility.
    2010s Hercules further investigated groundwater conditions, assessed potential risks, and planned additional remediation work.
    2012 Hercules investigated the outfall ditch to design the next phase of remediation.
    2014 The Wildlife Habitat Council (WHC) certified a wildflower field that was planted on a portion of the Brunswick facility.
    2015 WHC certified a portion of the 009 Landfill for its enhanced habitat for birds and reptiles.
    2015 EPA issued a proposed plan to remediate the outfall ditch at the Terry Creek site following more than seven years of investigation, planning and public meetings.
    2015 Hercules installed and later upgraded a shallow groundwater remediation system on-site.
    2017 EPA selected the final interim remedy for the outfall ditch to include capping the ditch and relocating the outfall. EPD concurred with the remedy selection.
    2018 The state relaxed fish consumption advisories again based on improvement in fish tissue sampling - a result of Hercules’ remediation.
    2018 Hercules committed through a consent decree to implement EPA's selected interim remedy and to reimburse EPA for all of its past and future costs.
    2019 Hercules remediated areas of toxaphene in soil and around the former toxaphene tank farm storage area.
    November 2019 A federal court in Georgia approved the consent decree for the interim remedy and found the agreement to be fair, reasonable, and in the public interest.
    2020 Hercules expanded forest habitat certified by WHC and continues to monitor nesting birds, pollinators, mammals, and forest habitat while taking care of the wildflower field.
    2020 Hercules added more grassland habitat to WHC program while monitoring birds, reptiles, amphibians, and pollinators.
    2020 EPD renewed the Brunswick facility's hazardous waste permit, for 10 years. The permit recognizes that hazardous wastes are no longer being stored at the Brunswick facility.
    2021 Hercules completed design of the interim remedy chosen by EPA for the outfall ditch. The remedy involves capping the existing ditch (where some residual contamination remains) and rerouting the ditch to the south.
    2021 Hercules completed remediation of contaminated soils at key locations around the Brunswick facility. Vapor intrusion mitigation systems were installed at various buildings on-site. EPD approved Hercules’ plan for source area groundwater treatment; Hercules proposed groundwater treatment plans to EPD for the eastern edges of the facility.
    2022 Hercules begins construction of the rerouted outfall ditch in late 2022.
    2022 Hercules treats source area shallow groundwater within process areas.
    2022 Hercules installed additional groundwater treatment wells at the 009 Landfill.
    June 2022 Hercules installed groundwater treatment wells and groundwater treatment begins at the southeastern edge of the facility.
    Dec 2022 EPD issues amended hazardous waste permit to incorporate planned remedial actions at the Brunswick plant outlined in the August 2022 Corrective Action Plan.
    April 2023 A fire at the terpene resins plant causes temporary shutdown of the Brunswick facility.
    June 2023 Pinova company representatives announce that the manufacturing facility will permanently close. Remediation work by Hercules and Pinova continues.
    2023 Hercules installed and activated groundwater treatment wells at the northeast edge of the facility.
    January 2024 Relocation of former outfall channel at Terry Creek is completed.
    2024 Groundwater treatment systems near Hwy 17 show reduction of target chemicals by more than 90%. Hercules voluntarily expands one of the treatment systems to broaden the positive impact.
    February 2024 Pinova leads efforts on demolition of all former plant related infrastructure to prepare the site for further remediation and ultimate sale and redevelopment.
    December 2024 Hercules installed additional treatment wells, expanding groundwater treatment along the southeastern edge of the facility.
    March 2025 Demolition activities across both Hercules' and Pinova's properties are completed.
    June 2025 Environmental covenants are put in place requiring any future development to adhere to environmental precautions and use restrictions.
    July 2025 With the final capping of the former outfall ditch, the OU1 remedial action is complete.
    July 2025 Over 2,000 tons of impacted soil are removed from the Marsh Wood Storage Yard in conjuction with the OU1 project completion.
    2025 EPA and Hercules continue to monitor the 009 Landfill remedy, that has been in place since the 1990s, to ensure its continued effectiveness.